Discharge of conditions 51 & 77
Decided: Permit
Original Application
Case Ref | Description | Posted on |
17/01759/AS | Proposed minor material amendments to planning permission 16/01157/AS involving design changes to Phase A2 (X3 commercial uses (Use Classes A1/A2/B1) &; Phase A3 (216 residential units) with associated parking, substations, landscaping and access works relating to land south of Victoria Road ONLY with no design changes to the approved development of land north of Victoria Road for the purposes of a brewery with shop, bar and restaurant (use classes B2/A1/A3/A4).Full planning application for development of a brewery, with shop, bar and restaurant (Use Classes B2/A1/A3/A4), three commercial units (Use Classes A1/A2/B1) and 216 residential units with associated parking, substations, landscaping and access works. | 12 Dec 2017 |
16/01157/AS | Full planning application for development of a brewery, with shop, bar and restaurant (Use Classes B2/A1/A3/A4), three commercial units (Use Classes A1/A2/B1) and 216 residential units with associated parking, substations, landscaping and access works. | 10 Aug 2016 |
Conditions
LAND FORMING PHASE A2 TO SOUTH OF VICTORIA ROAD (RESIDENTIAL AND COMMERCIAL – C3/B1/A1/A2/A3)
Acoustic design measures for apartments
-
- No development of land forming Phase A2 shall commence until a scheme of noise mitigation measures to be installed in the apartments (taking forward the noise related recommendations in the applicant’s acoustic report, energy strategy report and ventilation
strategy necessary to achieve BS8233:2014 ‘Guidance on sound insulation and noise reduction for buildings’ or any successor standard) has been submitted to, and approved by, the Local Planning Authority in writing. Thereafter, the development shall only be carried out in accordance with such approved measures which shall be permanently retained unless the Local Planning Authority has agreed in writing to any variation. - Unless agreed otherwise no development of land forming Phase A2 shall commence until a scheme for protecting balconies and terraces from noise exceeding 50dB LAeq. 16 hour through the use of including imperforate balustrade screens and Class A absorption to balcony undersides /soffits has been submitted to, and approved by, the Local Planning Authority in writing. Thereafter, the development shall only be carried out in accordance with such approved measures which shall be permanently retained unless the Local Planning Authority has agreed in writing to any variation.
- No development of land forming Phase A2 shall commence until a scheme of noise mitigation measures to be installed in the apartments (taking forward the noise related recommendations in the applicant’s acoustic report, energy strategy report and ventilation
LAND FORMING PHASE A3 TO SOUTH OF VICTORIA ROAD (RESIDENTIAL BUILDING)
Acoustic design measures for apartments
-
- No development of land forming Phase A3 shall commence until a scheme of noise mitigation measures to be installed in the apartments (taking forward the noise related recommendations in the applicant’s acoustic report, energy strategy report and ventilation
strategy necessary to achieve BS8233:2014 ‘Guidance on sound insulation and noise reduction for buildings’ or any successor standard) has been submitted to, and approved by, the Local Planning Authority in writing. Thereafter, the development shall only be carried out in accordance with such approved measures which shall be permanently retained unless the Local Planning Authority has agreed in writing to any variation. - Unless agreed otherwise no development of land forming Phase A3 shall commence until a scheme for protecting balconies and terraces from noise exceeding 50dB LAeq. 16 hour through the use of including imperforate balustrade screens and Class A absorption to balcony undersides /soffits has been submitted to, and approved by, the Local Planning Authority in writing. Thereafter, the development shall only be carried out in accordance with such approved measures which shall be permanently retained unless the Local Planning Authority has agreed in writing to any variation.
- No development of land forming Phase A3 shall commence until a scheme of noise mitigation measures to be installed in the apartments (taking forward the noise related recommendations in the applicant’s acoustic report, energy strategy report and ventilation
Amended to reflect decision