Planning Notice

Plots 3 4 and 5, Former Powergen site, Victoria Road – decided

Discharge of Conditions: 1 – Phasing (in respect of Plots 1-5) &; Part Discharge of Condition 63 – Heights, layout and access (in respect of Plot 3 only)

17/00018/CONA/AS

Decided: Permit

Original Application

17/00018/AS

Proposed variation of Condition 08 of planning permission 15/01671/AS to replace the following approved plans:-

  • Site Plan Proposed Illustrative Masterplan 14.046.S01.B
  • Plots 3, 4 &; 5 Block Plan 14.046.101 F
  • Parameter Plan Proposed Critical Distances 14.046.104 F
  • Parameter Plan Proposed Range of Building Heights 14.046.105 F
  • Parameter Plan Proposed Building Levels &; Plot Extents 14.046.106 G
  • Parameter Plan Proposed Access, Routes and Communal Landscaped Areas 14.046.107 G

Posted on 19 January 2017

15/01671/AS

Hybrid application for five plots comprising:

  1. Full and detailed application for plots 1 and 2 comprising: erection of 400 dwellings, a retail kiosk/cafe unit (Use class A1/A3) and associated parking, public surface car park, plant and storage; together with landscaping and access works.
  2. Outline application with appearance and landscaping reserved with parameters for plots 3, 4 and 5 comprising:  demolition of existing buildings/structures and erection of up to 260 dwellings, associated parking, plant and storage together with landscaping and access works.

Posted on 16 January 2016

Conditions

  1. Phasing Prior to the commencement of the development a plan showing the boundaries of each plot (including corresponding landscaped areas and car parking) shall be submitted to and approved in writing by the Local Planning Authority. If the plot boundaries subsequently change, a revised plan shall be submitted to and approved in writing by the Local Planning Authority. “Plot” in this permission means a plot as identified on the approved plan.
  1. Prior to the commencement of development of plots 3, 4 or 5 approval of the details of appearance and landscaping (hereinafter called “the reserved matters”) for each relevant plot shall be obtained from the local planning authority in writing and the development of each plot shall be carried out in accordance with those approved details. Details of final building heights, layout and access (internal circulatory access) in respect of each relevant plot (3, 4 and 5) shall also be submitted to and approved by the Local Planning Authority in writing before any development of the relevant plot commences. The submitted details shall be in accordance with the approved parameter plans. The development of each plot shall be carried out in accordance with those approved details.

Land between 1 Rose Villas and 25, Lower Denmark Road – decided

Erection of 4 no. two bedroom semi-detached houses, with associated car parking

17/00714/AS

Decided: Permit

Previous applications

relating to this site:

Case Ref Description Status
06/02397/AS Erection of five houses Decided: Disposed Of Undetermined
10/00082/AS Construction of 4 x two bedroomed detached houses and 2 x three bedroomed semi-detached houses on the site of former public house car park and beer garden. Withdrawn By Applicant
10/01300/AS Construction of 4 no. two-bedroomed semi-detached houses, with associated car parking on the site of former public house car park and beer garden Decided: Permit
10/01300/AMND/AS Application for a non material minor amendment to planning permission reference 10/01300/AS. Decided: Amended Plans Approved

Former Powergen site, Victoria Road – decided

Reserved Matters = Appearance and Landscaping

17/00658/AS

Decided: Approve Details (Reserved Matters)

 Original Application

Reference
Description
Posted on
15/01671/AS Hybrid application for five plots comprising:

  1. Full and detailed application for plots 1 and 2 comprising: erection of 400 dwellings, a retail kiosk/cafe unit (Use class A1/A3) and associated parking, public surface car park, plant and storage; together with landscaping and access works.
  2. Outline application with appearance and landscaping reserved with parameters for plots 3, 4 and 5 comprising:  demolition of existing buildings/structures and erection of up to 260 dwellings, associated parking, plant and storage together with landscaping and access works.
16 January 2016

 Amended by

Reference
Description
Posted on
 17/00018/AS Proposed variation of Condition 08 of planning permission 15/01671/AS to replace the following approved plans:-

    • Site Plan Proposed Illustrative Masterplan 14.046.S01.B
  • Plots 3, 4 &; 5 Block Plan 14.046.101 F
  • Parameter Plan Proposed Critical Distances 14.046.104 F
  • Parameter Plan Proposed Range of Building Heights 14.046.105 F
  • Parameter Plan Proposed Building Levels &; Plot Extents 14.046.106 G
  • Parameter Plan Proposed Access, Routes and Communal Landscaped Areas 14.046.107 G
19 January 2017

Amendments

Reference
Description
Posted on
17/00658/AMND/AS Plot 3 Design changes to building 3C, 4G, 4H and 4I and associated landscaping and access routes including revised planter locations and brick detailing 20 November 2018

 

Land at former Concorde House, Austin Road – decided

Discharge of conditions 9, 17, 18, 19, 21, 22, 23 &; 26

14/01515/CONB/AS

Decided: Permit

Original Application

14/01515/AS Erection of 4 x 2 bed houses and 10 x 3 bed houses with associated parking on existing commercial site. Provision of commercial parking posted on 27 May 2015

Conditions

  1. Details of a scheme for the protection and enhancement of biodiversity, including bat and bird boxes, use of native species in landscaping and incorporation of features beneficial to wildlife wherever possible within and around the perimeter of the site, together with the timing/phasing of the respective elements forming the scheme and proposed management arrangements, shall be submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be fully implemented prior to the occupation of the final dwelling on the site and thereafter maintained.
  1. No development approved by this planning permission shall take place until a remediation strategy that includes the following components to deal with the risks associated with contamination of the site shall each be submitted to and approved, in writing, by the local planning authority:
    1. A preliminary risk assessment which has identified:
      1. all previous uses
      2. potential contaminants associated with those uses
      3. a conceptual model of the site indicating sources, pathways and receptors iv. potentially unacceptable risks arising from contamination at the site.
    2. A site investigation scheme, based on (a) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off site.
    3. The results of the site investigation and the detailed risk assessment referred to in (b) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken.
    4. A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in (c) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action.

    Any changes to these components require the express written consent of the local planning authority. The scheme shall be implemented as approved.

  2. No occupation of any part of the permitted development shall take place until a verification report demonstrating completion of works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved, in writing, by the local planning authority. The report shall include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met. It shall also include any plan (a “long-term monitoring and maintenance plan”) for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action, as identified in the verification plan. The long-term monitoring and maintenance plan shall be implemented as approved.
  3. If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted a remediation strategy to the local planning authority detailing how this unsuspected contamination shall be dealt with and obtained written approval from the local planning authority. The remediation strategy shall be implemented as approved.
  1. Prior to the commencement of development, details of measures to be undertaken to protect the public sewers shall be submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details
  2. Prior to the commencement of development, details of the proposed means of foul and surface water sewerage disposal shall be submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the details.
  3. No development shall commence until plans and particulars of a sustainable drainage system (including the details below) for the disposal of the site’s surface water have been submitted to and approved in writing by the Local Planning Authority. The final drainage plan for the scheme will be approved by Ashford Borough council to ensure that surface water runoff from the site is being dealt with appropriately and in line with Ashford Borough Council’s Sustainable Drainage SPD. This will include a modified surface water drainage strategy which satisfies the requirements of the SPD. All discharging water runoff will be dealt with within the application boundary via suitable methods approved by Ashford Borough council where practicable. Proposals should identify any overland flow paths, channelling of flows, or piped flows along with the final point of discharge of the water from the site into a suitably agreed point of discharge. The submitted system shall comprise retention or storage of the surface water on-site or within the immediate area in a way which is appropriate to the site’s location, topography, hydrogeology and hydrology. The submitted system shall be designed to
    1. avoid any increase in flood risk,
    2. avoid any adverse impact on water quality,
    3. achieve a reduction in the run-off rate in accordance with the Ashford Borough council Sustainable Drainage SPD document, adopted October 2010.
    4. promote biodiversity,
    5. enhance the landscape,
    6. improve public amenities,
    7. return the water to the natural drainage system as near to the source as possible and
    8. operate both during construction of the development and post-completion.

    The submitted details shall include identification of the proposed discharge points from the system, a timetable for the provision of the system and arrangements for future maintenance (in particular the type and frequency of maintenance and responsibility for maintenance).

    The approved system shall be provided in accordance with the approved timetable. The approved system shall be maintained in accordance with the approved details and shall be retained in working order until such time as the development ceases to be in use.

    If the proposed surface water discharge point is to be the existing public sewer the applicant must provide written confirmation from Southern Water of their agreement to the proposals.

  1. Before any construction commences on the site the following shall be submitted to and approved in writing by the Local Planning Authority:
    • Code of Construction Practice;
    • Hours of working for construction;

    The development shall thereafter be carried out in strict accordance with the approved details unless otherwise agreed in writing by the Local Planning Authority