Former Pledges Mill and South Kent College Site, Victoria Road

Discharge of conditions: 25, 27, 28 & 32 in relation to Phase 1

16/01157/CONC/AS

Decided: Permit

Original Application

Case Ref Site Description of Works Posted on
16/01157/AS Former Pledges Mill and South Kent College Site and land south of junction of Beaver Road and, Victoria Road, Ashford, Kent Full planning application for development of a brewery, with shop, bar and restaurant (Use Classes B2/A1/A3/A4), three commercial units (Use Classes A1/A2/B1) and 216 residential units with associated parking, substations, landscaping and access works. 10 August 2016

Conditions

Code of construction practice
  1. Prior to the commencement of the development on land forming Phase A1, a Code of Construction Practice shall be submitted to and approval in writing by the Local Planning Authority. The construction of the development shall then be carried out in accordance with the approved Code of Construction Practice and BS5228 Noise Vibration and Control on Construction and Open Sites and the Control of dust from construction sites (BRE DTi Feb 2003).unless previously agreed in writing by the Local Planning Authority.
    The code shall include,

    • An indicative programme for carrying out the works
    • Measures to minimise the production of dust on the site(s)
    • Measures to minimise the noise (including vibration) generated by the construction process to include the careful selection of plant and machinery and use of noise mitigation barrier(s)
    • Maximum noise levels expected 1 metre from the affected façade of any residential unit adjacent to the site(s)
    • Design and provision of site hoardings
    • Management of traffic visiting the site(s) including temporary parking or holding areas
    • Full details of the provision of off-road parking for all site operatives
    • Full details of measures to prevent the transfer of mud and extraneous material onto the public highway
    • Measures to manage the production of waste and to maximise the re-use of materials
    • Measures to minimise the potential for pollution of groundwater and surface water • The location and design of site office(s) and storage compounds
    • The location of temporary vehicle access points to the site(s) during the construction works
    • The arrangements for public consultation and liaison during the construction works,including a programme for community consultation/communication setting out how the developers intend to liaise with and keep members of the public informed about the development for the duration of the construction period.
  1. No construction activities shall take place on the land forming Phase A1 until a dust management plan for the construction phase (in full compliance with the recommendations of the applicant’s Air Quality Report ref: AQA-19852-16-95) has been submitted to, and approved in writing by, the Local Planning Authority. Thereafter, the measures set out in the dust management plan shall be implemented in full for the subsequent full duration of construction works unless any variation has been agreed in writing by the Local Planning Authority.
  2. No construction works shall take place on the land forming Phase A1 until a construction logistics plan for the construction phase (in full compliance with the
    recommendations of the applicant’s Air Quality Report ref: AQA-19852-16-95) has been submitted to, and approved in writing by, the Local Planning Authority. Thereafter, the measures set out in the construction logistics plan shall be implemented in full for the subsequent full duration of construction works unless any variation has been agreed in writing by the Local Planning Authority.
  1. Development of the land forming Phase A1 shall only take place in accordance with the terms of a signed Basic Asset Protection Agreement with Network Rail Infrastructure Limited. A copy of the signed agreement shall be provided to the Local Planning Authority prior to commencement of development.